Project Accounting Progress Billing

Progress billing: bill the work done, net of what is held back

For each period, enter the gross work done. Adon ERP takes off retention, mobilization recovery, AIT and VDS, and gives the net payable. Retention builds up as a receivable until release.

See how a certificate is worked out

Now onboarding companies in Dhaka.

  • Interim payment certificates (IPCs) with period, gross work done and retention
  • Deductions for retention, mobilization recovery, AIT and VDS
  • Net payable worked out for each certificate
  • Retention held as a receivable until release at completion
AdonERP
Nodi Polymer Industries

Project Accounting

PRJ-AUTOMATION · Line Automation Upgrade

Retention held (receivable)

BDT 1,50,000

Retention payable (subcontractors)

BDT 40,000

Certified gross

BDT 15,00,000

Certified net payable

BDT 11,60,000

AIT deducted

BDT 90,000

VDS deducted

BDT 0

Mobilization recovered

BDT 1,00,000

Interim Payment Certificates· 1

+ New IPC

Net payable = gross − retention − mobilization recovery − AIT − VDS − other. Retention accrues as a receivable until release at completion; certified and paid IPCs feed the summary above.

IPC #GrossNet payableStatus
IPC-00115,00,00011,60,000certified

Subcontractor retention (AP)

Retention you withhold from each subcontractor or vendor bill on this project. Set a percentage; the amount is worked out from the bill’s pre-VAT subtotal and rolls into Retention payable above.

BillSubtotalRetention %
BILL-2026-000046 · Dhaka Machinery Co4,00,00010%

New IPC

Period from

mm/dd/yyyy

Period to

mm/dd/yyyy

Gross work done this period

0

Retention %

10

Mobilization advance recovery

0

AIT % (income tax at source)

6

VDS % (VAT at source)

0

Other deductions

0

Status

draft▾
CancelSave
A partial preview of Progress Billing in Adon ERP Project Accounting. Company, project and figures are sample data.

How an interim certificate is worked out

One line of arithmetic turns the work done into the money you will receive, and every deduction has its own box.

  1. Gross

    The work done this period

    Enter the gross value of the work done between two dates.

  2. Deductions

    What is taken off

    Retention, recovery of the mobilization advance, AIT at source, VDS at source, and anything else.

  3. Net

    What you will be paid

    Net payable is the gross less all deductions. Certified and paid certificates feed the summary cards.

What you fill in on a new IPC

Period from and to
The dates the certificate covers.
Gross work done
The value of the work in the period.
Retention %
The share held back until completion. Ten per cent here.
Mobilization recovery
What you take back of the advance already paid.
AIT and VDS
Income tax and VAT withheld at source, as percentages.
Other deductions, status and notes
Anything else, and whether the IPC is draft, certified or paid.

Progress billing turns work into invoices and cash

A certificate reads from the milestones and the quantities done, and feeds the receivables and the tax records.

Before the certificate

  • Milestones

    Milestones that can be billed.

  • BOQ

    Quantities done, for billing.

  • WIP

    Billed to date for WIP.

After the certificate

Where it shows up

Billing the way Bangladeshi contracts pay

Contracts pay in stages, with retention held back and tax taken at source. Knowing the net before you invoice avoids arguments later.

  • AIT at source

    Income tax withheld at source is taken off, and totalled in the summary.

  • VDS at source

    VAT deducted at source is tracked the same way.

  • Retention as a receivable

    What is held back is still yours, and the page keeps count.

  • Mobilization advance

    The advance is recovered over the certificates, not forgotten.

One certificate, from gross to net

A sample certificate, the way it usually runs.

  1. The period ends, and gross work done is 15,00,000 taka.

  2. Retention of 1,50,000 is held back.

  3. Mobilization recovery of 1,00,000 and AIT of 90,000 are taken off.

  4. Net payable comes to 11,60,000.

  5. The certificate is certified, and the summary cards update.

How different trades use progress billing

Questions we get about progress billing

What is an IPC?

An interim payment certificate: a statement of the work done in a period and the amount payable for it.

What is retention?

A share of each payment held back until the project is complete.

What are AIT and VDS?

Income tax and VAT withheld at source from a payment.

How is net payable worked out?

Gross less retention, mobilization recovery, AIT, VDS and other deductions.

Can I track retention on subcontractors?

Yes. Set a retention percentage on each subcontractor bill, and it rolls into Retention payable.

Where is Adon ERP available?

We are currently onboarding companies in Dhaka. Book a demo and we will walk through a sample project with you.

Bring a recent certificate. We will rebuild it, deduction by deduction, in the demo.

A live demo in English or Bangla, using sample books close to your own trade, with time for your accountant’s questions.

Explore Project Accounting